Enhanced Economics of Los Azules copper project

Share:

McEwen Mining Inc. announced the results of a new Preliminary Economic Assessment (PEA) on its 100% owned Los Azules Copper Project, located in San Juan province. The results of the 2017 PEA demonstrate that Los Azules is a robust, high margin, rapid pay-back, and long-life open pit mine at current copper, gold and silver prices.

Los Azules is a giant porphyry copper deposit that offers tremendous potential to generate wealth for McEwen Mining shareowners and other stakeholders,” said Rob McEwen, Chairman and Chief Owner. “Our next steps are to advance permitting and prefeasibility/feasibility studies to move Los Azules towards production. The reforms introduced by the government of Argentina under the leadership of President Macri to encourage mining investment by eliminating taxes on exported mineral concentrates was a key factor driving the new PEA for Los Azules”.

The 2017 PEA is a substantial revision of the previous 2013 PEA and contemplates an enhanced implementation strategy resulting in improved economics while reducing execution risk. It envisions an owner-operated mine and conventional concentrator (flotation circuit) producing a copper concentrate for export. A phased implementation approach is employed to optimise initial capital expenditure. Phase 1 implementation will have a daily throughput of 80,000 tonnes per day (tpd), and Phase 2 will deliver a 50% increase in the processing rate to 120,000 tpd. The process design has been modeled on the flowsheet and implementation of the recently constructed and operating Antapaccay (Glencore) copper concentrator located in the high Andes of Peru. Antapaccay shares many key characteristics with Los Azules, making it an obvious choice upon which to model the proposed infrastructure. Average annual copper production for the first 10 years would be in the order of 415 Million lbs.

Using the assumptions of $3.00/lb copper, $1,300/oz gold, and $17/oz silver, the Los Azules project generates a robust after-tax Net Present Value (NPV) discounted at 8% of $2.2 billion and an Internal Rate of Return (IRR) of 20.1%. The project economics for Los Azules contemplates two years of permitting, drilling, and feasibility studies; followed by a three year project implementation phase for production of the first copper concentrates. The economic values presented in the 2017 PEA are after-tax financial outcomes at the point of commencing the project implementation phase. The key financial results are summarized in Table 1

After-tax Financial Results

 

Parameter Unit 2017 PEA Result

 

Initial CAPEX $ millions 2,363

 

Phase 2 CAPEX $ millions 278

 

NPV8% $ millions 2,239
IRR % 20.1

 

Payback Period Years 3.6

 

C1 Costs (first 10 years) $/lb. 1.11

 

C1 Costs (Life-of-mine) $/lb. 1.28

C1 cash costs include at-mine cash operating costs, treatment and refining charges, mine reclamation and closure costs, and copper concentrate transportation.

Table 1 – Key Economic Parameters

 

The life-of-mine (LOM) ore tonnage is estimated to be 1,488 million tonnes of concentrator feed and 1,510 million tonnes of waste stripping. The stripping ratio, including stockpile re-handling, is projected at 1.05 (tonnes of waste per tonne of sulfide ore milled). Excluding the three-year preproduction period, the mine life is estimated at 36 years.

The concentrator feed during the first five years of operation is predicted to have a higher average grade of 0.73% copper. These grades are approximately double the average grades in the later years of mining (after Year 20). In the first five years of mining, 93% of this initial mill feed is presently classified as Indicated mineralized material and the remaining 7% is Inferred mineralized material.

 

Processing

Preliminary metallurgical test work has been conducted intermittently since 2008 to determine how the mineralized material responds to flotation as a means of recovering payable copper metal. Results have consistently proved favorable and flotation has been adopted as the processing option of choice.

The Los Azules concentrator will produce copper concentrate as a final product. The process flowsheet has been modeled on the Antapaccay copper concentrator (Glencore – Peru) due to similarities in ore properties and process plant altitudes. Some minor design changes, in equipment sizing only, have been incorporated based on operating experience at Antapaccay. The plant has been designed for average daily throughput of 80,000 tpd. The concentrator would be constructed on-site and would employ one comminution circuit consisting of a primary crusher, stockpile feed conveyor, reclaim conveyor, one SAG mill, two pebble crushers and two ball mills. The comminution circuit would be followed by flotation, thickening and filtration circuits, a Tailings Storage Facility (TSF) and concentrate storage. LOM recovery of copper to concentrate is expected to be 91% at a concentrate grade of 30% Cu.

It is planned to expand the capacity of the plant to 120,000 tpd by Year 5 through the installation of additional comminution and flotation capacity. Gold and silver are recoverable to the copper concentrate. No other metals have been identified that would yield by-product credits, nor that have significant amounts of penalty elements.

 

Capital Costs

A key desired outcome of this study was to provide a project capital estimate with a reasonable level of accuracy. A summary of the initial capital estimate is provided in Table 2.

Capital Cost Estimate
Area CAPEX

($ Millions)

 

Mining Equipment $             215
Mine Pre-stripping Cost $             193
Surface Scope (Concentrator, Power Line, Tailings, etc.) $             979

 

Total Direct Cost $             1,387 
Total Indirect Costs $             508 
Contingency $             420
Owner’s Cost $             48
Total Initial Capital Cost $             2,363 

Table 2 – Capital Cost Estimate

Publicado por: Panorama Minero

Categoría: Noticias

¿Querés recibir noticias del sector y de las iniciativas de Panorama Minero?


Suscribite a nuestro boletín.

Imagen ilustrativa para el artículo: Challenger Gold cierra colocación estratégica e inicia acuerdo de procesamiento en Casposo

Challenger Gold cierra colocación estratégica e inicia acuerdo de procesamiento en Casposo

La australiana Challenger Gold (ASX: CEL) anunció la finalización de una colocación estratégica por US$6,6 millones con una entidad controlada por Eduardo Elsztain, quien se convierte en el mayor accionista de la compañía con una participación del 12,7%. Además, se concretó el pago inicial de US$2 millones correspondiente al Acuerdo de Procesamiento por Peaje con Casposo Argentina Mining Limited, que asegura el procesamiento de 150.000 toneladas anuales de material de Hualilán durante tres años, con una capacidad total garantizada de 450.000 toneladas.
Imagen ilustrativa para el artículo: Galan Lithium obtiene permiso para expandir producción en Catamarca

Galan Lithium obtiene permiso para expandir producción en Catamarca

La junior australiana Galan Lithium Limited (ASX:GLN) recibió la aprobación del Ministerio de Minería de Catamarca para el permiso de explotación de Fase 2 en su proyecto de salmuera de litio Hombre Muerto Oeste (HMW). Este permiso habilita a la compañía a expandir su producción hasta 21.000 toneladas anuales de carbonato de litio equivalente (LCE), sujeto a la financiación del proyecto y tras la implementación de la Fase 1, que apunta a producir 5.400 toneladas anuales de LCE.
Imagen ilustrativa para el artículo: Jujuy: Caucharí-Olaroz superó las 25 mil toneladas de carbonato de litio

Jujuy: Caucharí-Olaroz superó las 25 mil toneladas de carbonato de litio

Lithium Argentina informó que su operación de salmuera de litio en Caucharí-Olaroz, ubicada en Jujuy, alcanzó una producción récord de aproximadamente 25.400 toneladas de carbonato de litio durante 2024, cumpliendo con sus metas anuales. Para 2025, la empresa proyecta un incremento en la producción, situándola entre 30.000 y 35.000 toneladas.
Imagen ilustrativa para el artículo: Catamarca: YMAD abre una licitación para equipamiento de la mina Farallón Negro

Catamarca: YMAD abre una licitación para equipamiento de la mina Farallón Negro

La empresa interestatal YMAD lanzó la Licitación Pública Nº 002/24 para adquirir un equipo tojeador de roca destinado a la mina subterránea Farallón Negro, ubicada en el departamento Belén, Catamarca. La convocatoria está dirigida a firmas interesadas en suministrar tecnología clave para operaciones mineras.
El empleo minero en Argentina cerró el 2024 con una tendencia a la baja

El empleo minero en Argentina cerró el 2024 con una tendencia a la baja

El año recientemente finalizado culminó con un panorama de desafíos para el empleo minero en Argentina, marcado por una caída sostenida en la generación de puestos de trabajo. Según el informe mensual de cierre de año publicado por la Secretaría de Minería en diciembre, durante el mes de agosto de 2024 se registraron 39.280 empleos formales directos en el sector minero. Estos datos, que forman parte de un análisis retrospectivo del año, muestran una disminución del 2,1% en comparación con agosto de 2023, lo que equivale a la pérdida de 824 puestos en un año y un total de 1.787 empleos menos durante los primeros ocho meses de 2024.
Lithium Argentina avanza con su traslado de sede corporativa a Suiza

Lithium Argentina avanza con su traslado de sede corporativa a Suiza

La empresa Lithium Americas (Argentina) Corp., conocida como Lithium Argentina, continúa avanzando en el proceso de trasladar su domicilio corporativo a Suiza y operar bajo el nuevo nombre de Lithium Argentina AG. Este cambio estratégico, anunciado originalmente el 29 de noviembre de 2024, se someterá a votación en una reunión especial de accionistas el próximo 17 de enero.
Minera Don Nicolás firma acuerdo de opción con Cerro Vanguardia S.A, para la venta de sus propiedades de exploración Michelle

Minera Don Nicolás firma acuerdo de opción con Cerro Vanguardia S.A, para la venta de sus propiedades de exploración Michelle

Cerrado Gold Inc. anunció que su subsidiaria 100% propiedad, Minera Don Nicolás S.A. (MDN), firmó un acuerdo de opción con Cerro Vanguardia S.A. (CVSA), una filial 100% propiedad de AngloGold Ashanti Holdings Plc, mediante el cual MDN ha otorgado a CVSA la opción de comprar un 100% de interés en ciertas propiedades ("Propiedades Michelle") ubicadas en la región sur de Minera Don Nicolás, en la provincia de Santa Cruz, por un total equivalente en pesos argentinos a US$14 millones (aproximadamente C$19 millones), sujeto al cumplimiento de ciertas condiciones.
El cobre, al rojo vivo

El cobre, al rojo vivo

Importantes proyecciones para el metal rojo. Argentina, con grandes posibilidades de desarrollar sus pórfidos de cobre.