Minsud updates exploration results in Chita Valley

Minsud updates exploration results in Chita Valley
Minsud updates exploration results in Chita Valley
Share:
Minsud Resources Corp. announced the receipt of assay results from five additional drillholes, which were completed as part of the ongoing Phase IV infill and scout drilling program at the Chita Valley Project, San Juan Province.

By Panorama Minero

Drilling has resumed on the infill drilling program covering an area of approximately 2.5 square kilometres, for the purpose of generating a Mineral Resource Estimate on the Property. This area represents the primary mineralized zone within the Chinchillones target, as delineated through drilling.

From February 2024, continued drilling in Phase IV focused along the NE-trending corridor at the eastern end of the Chinchillones target. To date, Minsud has completed 8,856m in 14 drillholes during the first half of 2024. Assays have been received for drillholes CHDH24-99 to CHDH24-103, totaling 3,736.6m.

Hole CHDH24-102 was drilled with an orientation of 315°/-65° to a depth of 743.70 metres. Significant Drill Intercepts include 527.7m @ 0.26% Cu, 9.70 g/t Ag and 0.16% Zn, from 216m depth, including 8.0m @ 3.85% Cu, 188.60 g/t Ag, and 1.28% Zn, from 386.0m depth. Hole CHDH24-103 was drilled with an orientation of 315°/-65° to a depth of 850 metres. Significant Drill Intercepts: o 384.0m @ 0.33% Cu, 5.85 g/t Ag, 85 ppm Mo, from 466.0m depth, including 15.0m @ 2.47% Cu, 0.22 g/t Au, 30.13 g/t Ag, and 0.159% Zn, from 548m depth.

Chichillones Infill Drilling Program Update

MSA continues the Chinchillones infill drilling program covering an area of approximately 2.5 square kilometres, for the purpose of generating a mineral resource estimate on the Property. The program comprises 27,488 metres of diamond drilling, distributed in 32 drillholes. A total of 13 drillholes totaling 9,838 metres (CHDH23-86 to CHDH23-98) were completed by the end of 2023, while an additional 8,856m in 14 drillholes was completed during the first half of 2024, for a total of 18,694 metres completed to date in the infill program.

Completed 2024 Roadmap Items:

• Flotation metallurgical testing at ALS Kamloops is ongoing. These metallurgical tests are a prerequisite for a maiden resource estimate on the Chinchillones polymetallic deposit discovery.
• Terraspec. TIMA, micro-XRF and QXRD mineralogical studies have been completed in representative samples from the 2023 drillholes.

Ongoing 2024 Roadmap Items:
• Continuation of the remainder of the infill program of approximately 17,650 metres, expected to be completed by Q3 2024.
• Continuation of metallurgical testing on representative domains. Establish high, medium, and lowgrade domains for metallurgical and recovery testing.
• Continuation of mineralogical studies, Terraspec, TIMA, and QXRD on samples.
• Beginning in Q4 2024, continue with the development of new Exploration Targets identified during geological mapping surveys completed in 2023.
• Completion of an NI 43-101 resource estimate at the Chinchillones area within the Chita Valley Project by the end of Q4.

Current exploration activities on the Chita Valley Project are being funded by South32 Limited. On April 5, 2024, Minsud completed the issue to a wholly-owned subsidiary of South32 of a 50.1% shareholding in Minera Sud Argentina S.A. (“MSA”), Minsud’s indirect Argentinian subsidiary that holds and operates its flagship Chita Valley Project. The issue was made in accordance with South32’s earn-in right under the earn-in agreement dated November 1, 2019.

Noti 20240701 IMAGEN.jpg

Published by: Panorama Minero

Category: News

Join our mining community!


Subscribe to our newsletter for exclusive news, insights, and updates on the mining industry and Panorama Minero's latest initiatives.

Illustrative image for the article: Aldebaran Announces Commencement of 2024/2025 Altar Project Field Program

Aldebaran Announces Commencement of 2024/2025 Altar Project Field Program

Aldebaran Resources Inc. announced that field activities are underway and drilling has commenced at the Altar project in San Juan province.. The Company has secured five drill rigs for the 2024/2025 field program, with an option on a sixth, and is targeting approximately 25,000 m of drilling.
Illustrative image for the article: Events: The Mining Industry Gathers in Buenos Aires to Close Out 2024

Events: The Mining Industry Gathers in Buenos Aires to Close Out 2024

Panorama Minero will organize its double event, "Argentina Gold, Silver & Copper" and the annual sector dinner "The Mining Awards Night", on December 4-5 in Buenos Aires, with an estimated audience of over 650 people. This platform will highlight the current state of the mining industry.
Illustrative image for the article: Mendoza Senate Approves Copper Exploration in 34 Projects in Malargüe

Mendoza Senate Approves Copper Exploration in 34 Projects in Malargüe

With a broad majority, the Mendoza Senate has approved the environmental impact declarations for 34 copper exploration projects in the Western Mining District of Malargüe, opening the door to mining activities in the southern part of the province. This decision, already endorsed by the Chamber of Deputies, was ratified with 33 votes in favor and only 3 against, reflecting political consensus on the importance of this initiative for the regional economy.
Illustrative image for the article: San Juan: Minas Argentinas Unveils $1 Billion Investment Plan under RIGI Program

San Juan: Minas Argentinas Unveils $1 Billion Investment Plan under RIGI Program

Mining company Minas Argentinas SA, a subsidiary of AISA Group and operator of the Gualcamayo mine, has submitted a $1 billion investment plan to Argentina’s Incentive Regime for Major Investments (RIGI), making it the first company in San Juan to join this program. This marks the largest proposed investment under the RIGI in the region, with the potential to bring significant economic and employment opportunities.
Renewable Energy: Genneia Announces Commissioning of La Elbita Wind Farm

Renewable Energy: Genneia Announces Commissioning of La Elbita Wind Farm

Genneia, a renewable energy company, has announced the commissioning of La Elbita Wind Farm, its eighth wind project in Argentina and third in the province of Buenos Aires. Located 42 kilometers from Tandil, this project represents an investment of over $240 million and marks a significant milestone in the company’s wind power capacity in the country.
Arcadium Lithium Reports Q3 Results Amid Acquisition by Rio Tinto

Arcadium Lithium Reports Q3 Results Amid Acquisition by Rio Tinto

The lithium company, which is set to be acquired by Rio Tinto, reported third-quarter revenues of US$203.1 million, with attributable net income of US$16.1 million and adjusted EBITDA of US$42.9 million. Despite a decrease in volumes and market prices for certain products, the company managed to maintain an average price of US$16,200 per metric ton of lithium. This figure represents a slight decline from the previous quarter, driven primarily by weaker demand and delays in the lithium carbonate production expansion at the Olaroz project in Argentina.
Latin Metals Strengthens its Presence in Argentina’s Metal Mining Sector

Latin Metals Strengthens its Presence in Argentina’s Metal Mining Sector

Vancouver-based mining company Latin Metals Inc. announced that it has fulfilled the necessary payment obligations to secure a 71% ownership stake in the Cerro Bayo and La Flora exploration projects, located in Argentina’s Santa Cruz Province. This acquisition strengthens its precious metals portfolio in a highly prospective area, amid a strong wave of investor interest in Argentina’s mining hubs. The company also retains an option to acquire 100% of the properties, subject to a 0.75% NSR (Net Smelter Return) royalty.