Cerrado Gold announced Q4 and annual 2023 gold production results for its Don Nicolas Mine in Argentina

4 mins reading
Cerrado Gold announced Q4 and annual 2023 gold production results for its Don Nicolas Mine in Argentina
Cerrado Gold announced Q4 and annual 2023 gold production results for its Don Nicolas Mine in Argentina
Share:

Cerrado Gold Inc. announced production results for the fourth quarter of 2023 from the Minera Don Nicolas Mine in Santa Cruz Province, Argentina.Full financial results are expected to be released in late April 2024.

By Panorama Minero

Operational results presented for Q4 2023 continued to be impacted by the slower than expected ramp-up of the Calandrias Heap Leach project during the quarter while a new crushing system was installed. The crushing unit is now operational, and mining rates are reaching planned capacity. Production is set to ramp-up over the first quarter of 2024 and achieve nameplate production rates from April thereafter. At Calandrias Norte, stripping activities were largely completed during the quarter and the pit is now beginning to deliver ore to the CIL plant at Martinetas. Ore is expected to fill the mill by mid-February onward. Head grades from Calandrias Norte are reconciling well with the model and grades are expected to increase as early benches are mined and deeper, higher grade levels accessed.

While production levels have begun to improve, the delay in the ramp up of the heap leach operations, the costs associated with stripping at Calandrias Norte and debt repayment associated with capital projects have had an impact on the financial performance at MDN. Newly introduced fiscal policies that have resulted in hyper-inflation have also had a significant impact on the operations of the business particularly as suppliers react to the new fiscal regime in Argentina.

Q4 Operating Highlights

-Q4 2023 GEO production of 15,202 ounces and annual GEO production of 51,688 ounces for 2023.

-Ramp-up of production from the Las Calandrias heap leap project continues; commercial production delayed to end of Q1 2024.

-Pre-strip at Calandrias Norte largely complete and higher-grade ore beginning to feed the mill.

-Major capital programs at MDN complete, with current focus on delivering cashflow, rebuilding the balance sheet and longer-term exploration and mine life extension.

Mark Brennan, CEO and Chairman commented, "While the second half of the year has been challenging starting with unusually harsh winter conditions in August resulting in a slower ramp up at the heap leach, we see operations at MDN positioned to turn the corner in February as we access higher grade ore from Calandrias Norte and the leach cycle at Las Calandrias normalizes. That said, recent changes to fiscal policies in Argentina have resulted in a highly inflationary environment, impacting operations as costs have increased and suppliers have reduced payment terms. The focus at MDN will move to generating cashflow from our capital investments in 2023 that allow us to rebuild the balance sheet and refocus our efforts on exploration and increasing the overall life of mine at MDN."

Stripping at Calandrias Norte continued during the quarter. The Pre-Strip is now largely complete, allowing for fresh ore to fully feed the mill.

Ore milled increased during the fourth quarter as operations normalized. Production rates improved in Q4 as the operating environment returned to normal. However, additional gold production expected from the heap leach has been limited in the 4th quarter as irrigation was paused to allow for the completion of the installation of the new crushing circuit. Total production from the heap leach in the 4th quarter was 531 ounces.

Ongoing work to optimize mine sequencing and exploration work to upgrade and define new sources of resources remains the key focus of development at MDN. The operations team is focused on numerous new growth projects aside from expanding current open pit resources, including the completion of the ramp up of Las Calandrias Heap Leach operation and the review of a potential new Heap Leach operation at Martinetas.

Published by: Panorama Minero

Category: News

Join our mining community!


Subscribe to our newsletter for exclusive news, insights, and updates on the mining industry and Panorama Minero's latest initiatives.

Illustrative image for the article: Rare Earth Elements: What Resources Does Argentina Have?

Rare Earth Elements: What Resources Does Argentina Have?

They’re not truly rare, but they are hard to access. Rare earth elements (REEs) are critical to the world’s technological, military, and energy transitions. China dominates the market, but Argentina is beginning to assess its potential.

Illustrative image for the article: Techint E&C: “We Are Ready to Begin Working on Large-Scale Mining Projects in Argentina”

Techint E&C: “We Are Ready to Begin Working on Large-Scale Mining Projects in Argentina”

Techint Engineering and Construction participated for the first time in Arminera together with TAKRAF Group, a company that provides innovative solutions for the mining industry and is also part of the Techint Group. The presence was not symbolic: it marks a strategic decision of Techint E&C to approach the Argentinean mining ecosystem with a concrete proposal.

Supervielle Targets Swift Financing for the Mining Supply Chain and Has Already Disbursed Over US$10 Million to Suppliers

Supervielle Targets Swift Financing for the Mining Supply Chain and Has Already Disbursed Over US$10 Million to Suppliers

Ignacio Morello, Chief Corporate Banking Officer at the bank, outlines the strategy behind the +Mining unit, which is focused on meeting the financing needs of Argentina’s mining ecosystem. Instruments such as leasing, invoice-based lending, and capital markets funding are helping providers invest—even when they lack a strong financial track record. “We’ve managed to disburse funds to mining companies in less than 24 hours,” he says.

"Mining Accounts for 10% of Scania’s Sales in Argentina"

"Mining Accounts for 10% of Scania’s Sales in Argentina"

In an interview with Panorama Minero, Juan Pablo Cagnola, Area Sales Manager and head of the mining segment at Scania Argentina, analyzes the current landscape for heavy transport, emerging technology trends in mining, and the logistical challenges of operating in extreme environments. The company highlights the key role of digitalization, tailored technical support, and improved economic policy conditions in facilitating investment.

The European Union Brings Key Financial Delegation to Discuss Investments in Lithium and Copper

The European Union Brings Key Financial Delegation to Discuss Investments in Lithium and Copper

The European Union (EU) has identified lithium, copper, cobalt, nickel, gallium, boron, and rare earth elements as critical minerals essential to the energy transition and technological innovation. In this context, it launched a series of initiatives aimed at diversifying its supply sources—primarily to reduce dependence on China—by promoting the extraction, processing, and recycling of these minerals within its own borders.