LSC Lithium: Progress on Infrastructure for the Pozuelos-Pastos Grandes Project

Share:

LSC Lithium Corporation announced progress on key infrastructure for the Pozuelos-Pastos Grandes (“PPG”) Project. The Company has engaged with regulators and Salta based service providers to advance permitting, data acquisition and construction of key project infrastructure.

 

Highlights

  • Allocation of gas capacity to support electricity and steam generation for 20k tpa lithium carbonate operation.
  • Fresh water sources identified with quality confirmed for future operations.
  • Commencement of geotechnical investigations for ponds and plant infrastructure covering approximately 800 ha in the Pozuelos salar.
  • Completion of exploration camp which will be converted and expanded to a future operations camp.
  • Application submitted for permit for brine pipeline corridor connecting Pastos Grandes and Pozuelos with approval expected in Q1 2019. This will secure the planned production mix of approximately 35% of brine from Pastos Grandes and 65% from Pozuelos, providing an efficient blend.

LSC’s President and CEO Ian Stalker, noted, “The PPG Project is well located in direct vicinity to existing road and gas infrastructure. I am pleased with the progress made by the in-country team in advancing the various workstreams to confirm access to this infrastructure. The identification of sites well suited to pond and plant construction confirm our belief that Pozuelos can serve as host for a standalone lithium production system with brine supplied from Pozuelos and the adjacent Pastos Grandes salar. We are particularly pleased by the presence of several sources of fresh water proximate to our PPG Project. Equally, the allocation of gas capacity is an important development milestone and places the PPG Project ahead of other junior developers in the region.”

 

Allocation of Gas Capacity

LSC has received written confirmation from the gas distribution company allocating capacity on the existing Puna and Fenix gas pipelines. The quantities are expected to be sufficient to produce electricity and steam generation for a production facility of 20,000 tpa of lithium carbonate.

The intention to tie into the existing Fenix pipeline approximately 40 km south of Pocitos and connect directly to the Pozuelos salar is supported by the distributor. LSC will continue this engagement to finalize technical specifications, price assumptions, and understand infrastructure requirements.

 

Completion of Exploration Camp

The construction of a 40-person exploration camp at the Pozuelos salar has been completed and was occupied in September. The camp will simplify future exploration logistics, support the construction and operation of future pilot ponds and has been designed to be expanded for future mine operations. Once the PPG Project is moved to construction and production, this camp will be expanded and utilized for mine administration offices and as an operational camp.

 

Fresh Water Supply

Three separate sources of fresh water have so far been identified across the Pozuelos salar. Fresh water at site WWF1, which is located approximately 1 km from the accommodation camp, will be used to support the camp operations and future pilot plant test work.

Sites PZMW01 and PZMW02 were drilled to test the brine-fresh water interface in the extreme north and south of the Pozuelos salar. The testing confirmed a conventional interface, with fresh water recharging the salar above a layer of brackish water and brine lower in the stratigraphy.

The quality of water at all three sites supports water requirements for a future process plant with minimal treatment. Testing is ongoing to ascertain the long term yield potential from these wells. An application for a water abstraction permit has been lodged with the Ministry of Environment in August 2018 with approval expected before the end of the year.

 

Commencement of Geotechnical Investigations

A first field investigation was undertaken by a geotechnical engineer to ascertain and confirm that conditions within the salar support the construction of the primary evaporation ponds which are expected to be approximately 800 ha in size. Furthermore, sufficient area is available adjacent to the salar for placing the secondary and tertiary ponds, salt stockpiles and the lithium plant. A program is now being developed to confirm detail design criteria for building foundations and pond construction.

 

Pipeline Connection Corridor

LSC plans to deliver approximately 35% of raw feed brine to the evaporation ponds from the Pastos Grandes salar. A pipeline of approximately 15 km in length is required to transport this brine. As 11 km of this pipeline is located outside of LSC tenements, an application for an easement for the pipeline corridor has been submitted to the Salta mining authorities. This application was supported by an environmental impact assessment and baseline studies over the extent of this pipeline corridor. Approval is expected in Q1, 2019.

This approach ensures that all major project infrastructure can be located in the mature Pozuelos salar, where geotechnical, environmental, physical and social conditions are better suited to the construction of infrastructure.

Publicado por: Panorama Minero

Categoría: Noticias

¿Querés recibir noticias del sector y de las iniciativas de Panorama Minero?


Suscribite a nuestro boletín.

Imagen ilustrativa para el artículo: Lithium Argentina avanza con su traslado de sede corporativa a Suiza

Lithium Argentina avanza con su traslado de sede corporativa a Suiza

La empresa Lithium Americas (Argentina) Corp., conocida como Lithium Argentina, continúa avanzando en el proceso de trasladar su domicilio corporativo a Suiza y operar bajo el nuevo nombre de Lithium Argentina AG. Este cambio estratégico, anunciado originalmente el 29 de noviembre de 2024, se someterá a votación en una reunión especial de accionistas el próximo 17 de enero.
Imagen ilustrativa para el artículo: Minera Don Nicolás firma acuerdo de opción con Cerro Vanguardia S.A, para la venta de sus propiedades de exploración Michelle

Minera Don Nicolás firma acuerdo de opción con Cerro Vanguardia S.A, para la venta de sus propiedades de exploración Michelle

Cerrado Gold Inc. anunció que su subsidiaria 100% propiedad, Minera Don Nicolás S.A. (MDN), firmó un acuerdo de opción con Cerro Vanguardia S.A. (CVSA), una filial 100% propiedad de AngloGold Ashanti Holdings Plc, mediante el cual MDN ha otorgado a CVSA la opción de comprar un 100% de interés en ciertas propiedades ("Propiedades Michelle") ubicadas en la región sur de Minera Don Nicolás, en la provincia de Santa Cruz, por un total equivalente en pesos argentinos a US$14 millones (aproximadamente C$19 millones), sujeto al cumplimiento de ciertas condiciones.
Imagen ilustrativa para el artículo: El cobre, al rojo vivo

El cobre, al rojo vivo

Importantes proyecciones para el metal rojo. Argentina, con grandes posibilidades de desarrollar sus pórfidos de cobre.
Economía Circular

Economía Circular

En la actual economía lineal globalizada, basada en el paradigma de "tomar, fabricar y desechar", las agendas globales están cada vez más orientadas hacia la neutralidad de carbono, con el fin de garantizar un futuro sostenible. En este contexto, el rol de la minería es clave en la transición hacia fuentes de energía bajas en carbono, dado que provee las materias primas e insumos necesarios para tecnologías más limpias. Por ello, la continuidad y expansión de la minería deben alinearse con las crecientes demandas sociales y ambientales que limitan el acceso a los yacimientos.
Proyecto Altar: Aldebaran informa que Nuton realizará el segundo pago del Acuerdo de Opción

Proyecto Altar: Aldebaran informa que Nuton realizará el segundo pago del Acuerdo de Opción

El 23 de diciembre, Aldebaran Resources Inc. anunció que Nuton Holdings Ltd., una empresa conjunta de Rio Tinto, ha confirmado que realizará el segundo pago (US$20 millones) conforme al Acuerdo de Opción para la Asociación en Empresa Conjunta con Aldebaran, anunciado el 7 de noviembre de 2024. Aldebaran anticipa recibir el pago a principios de enero de 2025.
Banco San Juan otorga préstamo para la planta de Casposo

Banco San Juan otorga préstamo para la planta de Casposo

El productor de oro Austral Gold Limited, anunció que Casposo Argentina Ltd. – Sucursal Argentina (Casposo), una filial de la empresa Casposo Argentina Mining Ltd., obtuvo un préstamo garantizado de US$7 millones del Banco San Juan S.A., entidad localizada en Argentina.
Lunahuasi: NGEx alcanza mineralización de cobre y oro de alta ley

Lunahuasi: NGEx alcanza mineralización de cobre y oro de alta ley

NGEx Minerals Ltd. proporcionó la primera actualización sobre su programa de perforación en curso de la Fase 3 en el proyecto de cobre-oro-plata de alta ley Lunahuasi, localizado en la provincia de San Juan. La perforación comenzó a mediados de octubre de 2024, y actualmente hay seis equipos de perforación diamantina trabajando en el proyecto.